DHA Karachi building approvals, step by step

To build a custom home in DHA Karachi you have to comply with the DHA Karachi Building Control and Town Planning Regulations 2020. This guide sets out the approvals you need, and then the design rules your plans must meet.
Modern white two-storey home with a timber slat screen and wooden gate

Step 1: the documents you need before you break ground

Before you start on a residential plot in DHA Karachi you need:

  • An updated Site Plan from the DHA office, which stays valid for two years from the date of issue
  • A valid A’ Lease, which gives you full leasehold rights to build

Step 2: plan approval

Your architectural drawings and structural calculations are submitted to DHA Karachi for first vetting. Once they are verified, the plans go to the Military Estate Office (MEO) and the Clifton Cantonment Board (CBC) for final approval.

Step 3: No Objection Certificates during construction

While you build, inspectors issue No Objection Certificates (NOCs) at critical milestones, including excavation, foundation laying,
basement formation and plinth level verification. Skipping a stage can lead to fines or a halt to construction.

Step 4: the completion certificate

When construction is finished, DHA Karachi and the Clifton Cantonment Board inspect the building against the approved plans, checking
open spaces, total height, window positions and boundary walls. Any unapproved change must be put right before a Completion
Certificate is issued. Utility providers ask for the certificate before they give permanent water, gas and electricity connections.

Living room with a grey sofa, marble coffee table and dark stone feature wall

Design rules your plans must follow

Alongside the approvals, your plans have to meet rules on open space, height and structure.

Reception area with a slatted timber ceiling and a lattice screen

Design rule: compulsory open spaces

The regulations require compulsory open spaces (COS) around a residential building, for light, ventilation and consistency. The size depends on the plot, and permanent concrete structures, extended balconies or unapproved overhangs may not encroach on them.

Hallway with a patterned lattice screen and a built-in bench on marble flooring

Design rule: height, floors and basements

Residential rules set height limits and floor area ratios. A basement is allowed, but the rules cover excavation depth, retaining walls and soil retention, and a basement needs natural light wells and ventilation.

Meeting room with a long table, black chairs and a wall-mounted screen

Design rule: structural design

Karachi sits in seismic zone 2B. DHA regulations require soil testing reports before the structural drawings are made, and a licensed structural engineer must design and sign off the foundation, column and slab details

Office reception with a curved black staircase, front desk and potted plants

Rules can change

These rules can change. Check the current DHA Karachi regulations, or ask us, before you start.

Questions and answers

What do I need before I can start building in DHA Karachi?
An updated Site Plan from DHA, a valid A’ Lease, and approval of your architectural and structural plans by DHA, the Military Estate Office and the Clifton Cantonment Board.
Basements are allowed under the bylaws, but they must follow the rules for excavation, retaining walls and ventilation, and a certified structural engineer must design the foundation and retaining walls.
After construction, DHA and CBC inspectors check the building against the approved drawings. When it passes, the Completion Certificate is issued, and it is needed for permanent utility connections.

DHA Karachi building approvals, step by step

To build a custom home in DHA Karachi you have to comply with the DHA Karachi Building Control and Town Planning Regulations 2020. This guide sets out the approvals you need, and then the design rules your plans must meet.

Steps 1 to 4: the approvals

Documents before you break ground, plan approval, No Objection Certificates during construction, and the completion certificate.

Design rules your plans must follow

Open space, height, floors, basements and structural design. For the full rules, read our DHA Karachi building bylaws article.

Rules can change

These rules can change. Check the current DHA Karachi regulations, or ask us, before you start. Back to